Essays.club - Get Free Essays and Term Papers
Search

Solar Power on the Rise

Autor:   •  March 5, 2018  •  4,130 Words (17 Pages)  •  555 Views

Page 1 of 17

...

---------------------------------------------------------------

- EARNED VALUE TABLE WITH PERCENTAGE OF TASKS COMPLETE

Duration (in weeks)

5 10 15 20 25 30 35 40 45 % Comp.

[pic 72][pic 73]

Design 6 2 100

Engineer 4 8 8 8 100

Install 4 20 6 50

Test 2 6 4 2 0

Total 6 6 8 12 28 8 6 4 2

Cumul. 6 12 20 32 60 68 74 78 80

---------------------------------------------------------------

- CALCULATING EARNED VALUE

(All numbers are in thousands $)

Planned % Comp. Earned Value

[pic 74][pic 75]

Design 8 100 8

Engineer 28 100 28

Install 30 50 15

Test 14 0 0

Cumul.

Earned 51

Value

---------------------------------------------------------------

13.9 PROJECT BASELINE, USING EARNED VALUE

Cumulative Cost

($ in thousands)[pic 76]

80[pic 77][pic 78]

[pic 79][pic 80][pic 81]

Project Baseline[pic 82]

60[pic 83][pic 84]

Earned Value[pic 85][pic 86][pic 87]

40[pic 88][pic 89]

[pic 90][pic 91][pic 92]

20[pic 93][pic 94]

[pic 95][pic 96][pic 97]

[pic 98][pic 99][pic 100]

[pic 101][pic 102][pic 103][pic 104][pic 105][pic 106][pic 107][pic 108][pic 109][pic 110][pic 111]

5 10 15 20 25 30 35 40 45

Elapsed Time (in weeks)

- EARNED VALUE MILESTONES

[pic 112]

AC[pic 113][pic 114]

Actual[pic 115][pic 116][pic 117]

Overspend

Cost[pic 118]

PV EV[pic 119]

Budget[pic 120][pic 121][pic 122][pic 123]

Slip[pic 124][pic 125]

[pic 126]

Schedule Performed

Schedule[pic 127][pic 128]

- EARNED VALUE TABLE

Activity Jan Feb Mar Apr May Jun Jul Plan % C Value

Staffing 8 7 15 100 15

Blueprinting 4 6 10 80 8

Prototype

Devel 2 8 10 60 6

Full Design 3 8 10 21 33 7

Construction 2 30 32 25 8

Transfer 10 10 0 0

Punch List 15 5 20 0 0

Σ = 118 44

Monthly Plan 8 7 6 17 10 55 15

Cumulative 8 15 21 38 48 103 118

Monthly Actual 8 11 8 11 10 30 0

Cumulative

Actual 8 19 27 38 48 78

---------------------------------------------------------------

13.12 SCHEDULE VARIANCES FOR EVM

Schedule Variances

Planned Value (PV) 103

Earned Value (EV) 44

Schedule Performance Index EV/PV = 44/103 = .43

Estimated Time to Completion (1/.43 x 7) = 16.3 months

---------------------------------------------------------------

13.13 COST VARIANCES FOR EVM

Cost Variances

Actual Cost of Work (AC) 78

Earned Value (EV) 44

Cost Performance Index EV/AC = 44/78 = .56

Estimated Cost to Completion (1/.56 x $118,000) = $210,714

---------------------------------------------------------------

13.14 CRITICAL SUCCESS FACTORS IN PROJECT IMPLEMENTATION

- PROJECT MISSION

- TOP MANAGEMENT SUPPORT

- PLANS AND SCHEDULES

- CLIENT CONSULTATION

- PERSONNEL

- TECHNICAL TASKS

- CLIENT ACCEPTANCE

- MONITORING AND FEEDBACK

- COMMUNICATION

- TROUBLE-SHOOTING

DISCUSSION QUESTIONS

- Why is the generic four-stage control cycle useful for understanding how to monitor and control projects?

One of the more

...

Download:   txt (28.9 Kb)   pdf (92.4 Kb)   docx (36.6 Kb)  
Continue for 16 more pages »
Only available on Essays.club