Summer Internship Project Report on Functions, Working and Exploration of Various Departments/areas of the Organization
Autor: Rachel • April 23, 2018 • 2,237 Words (9 Pages) • 850 Views
...
permit
• Near miss
• First aid case
• MOM: Minutes of meeting
• Training record
• Housekeeping schedule
• PPE inspection
• Third party inspection
• Inspection of FBH
• Fire extinguisher
• SDP
• Traffic management plan
• First aid file
• Emergency rescue plan
• Motivational program
• ISA
Following are some illustrations available:
(Table 1: Tool Box Talk)
(Table 2: Safety Task Assignment)
b) Safety task assignment 1
(Table 3: Safety Task Assignment)
(Table 4: MC/HP/RA Checklist)
(Table 5: MC/HP/RA Checklist)
(Table 6: Safety Inspection of Gas Cutting Permit)
(Table 7: Hot work permit)
Site Analysis Examples:
• Clamping in scaffolding
• Toe rod during welding
• Barricading the openings
• Safety belts for the workers during WAH(Work at height)
• SDP (Safety driving permit) for the drivers of various vehicles, equipments. etc.
• Labour motivation
• Solving Conflicts
• PPE Checks
• Different training for Different tasks (Scaffolding, Confined space, Grinding, Crushing, WAH)
Chapter 2
Quality
Quality Guides:
Mr. Kamlesh Patel, Mr. Neeraj Kumar, Mr. Aniket Modi
Documentation (RIL & GDCL):
• QAP (Quality assurance plan):
Includes commitments and promises by contractor (GDCL) to the Client (RIL).
QA: Quality assurance QC: Quality control
• ITP (Inspection and Testing plan):
Includes all the inspection and testing details of materials, equipments, machines, etc.
• Specifications:
Includes all the detailed specification such as size, type, amount, brand of equipments, materials, etc. according to IS codes as well as few modifications by RIL.
• QMS (Quality management system):
A quality management system (QMS) is a set of policies, processes and procedures required for planning and execution (production/development/service) in the core business area of an organization. (i.e. areas that can impact the organization’s ability to meet customer requirements.)
• FOR (Field observation report) :
Report generated by client to contractor for an improper execution work observed at site after a single inspection.
• NCR (Non confirmation report) :
Report generated by client to contractor for an improper execution work observed at site even after submission of FOR.
• Punch List:
Prepared by quality engineer, includes all the site work execution with the exact location that is to be modified or rectified.
• Material testing:
Includes all the testing reports prepared by the quality engineer.
Site Analysis:
• Precast yard visit
• Cast in situ visit
• Laboratory visit
• Crack repair
• Honey comb, cracks identification
• Identifying the need of grouting
Chapter 3
Execution
Execution Guides:
Mr. Jay Prakash Das
Initial task:
To study structural, engineering drawings such as:
• MEG plot plan
• Vent gas compressor plan (RC details of equipment foundation)
• GA & RC details of E-W sub pipe rack
& many more.
Documentation:
• Project Control:
Project controls are the data gathering, management and analytical processes used to predict, understand and constructively influence the time and cost outcomes of a project or program; through the communication of information in formats that assist effective management and decision making.
• Drawing Control:
A register that involves the records for each drawing of a project, i.e. the originals as well as the revised ones.
• Schedule Control:
It involves a detail such as time, amount and location schedule of each activity that is to be performed on site.
e.g.: Excavation.
• Weekly Concrete Plan:
...