From this chart the expected duration, standard deviation, activity slack, and critical path duration can be calculated in the following chart.
[pic 2][pic 3]
Time (days)
Activity
Critical
CP
CP
Activity
Mean
Var
Slack
Path?
Duration
Variance
A
4.17
0.25
0
yes
4.17
0.25
B
3.17
0.25
0
yes
3.17
0.25
C
3.83
0.25
3.8
D
2.17
0.25
26.5
E
2.00
0.11
0
yes
2.00
0.11
F
3.83
0.25
3.8
G
3.17
0.25
0
yes
3.17
0.25
H
4.17
0.69
4.2
I
2.83
0.25
6.2
J
2.17
0.25
0.5
K
5.17
0.69
0
yes
5.17
0.69
L
6.50
0.69
6.0
M
8.33
1.00
0
yes
8.33
1.00
N
3.33
0.44
6.0
O
2.33
0.44
6.0
P
3.50
0.69
6.0
Q
4.17
0.25
0
yes
4.17
0.25
R
6.33
1.00
6.0
S
5.83
2.25
4.8
T
4.33
1.00
0
yes
4.33
1.00
U
3.33
0.44
5.1
V
6.33
1.00
0
yes
6.33
1.00
W
5.00
1.00
0
yes
5.00
1.00
X
2.83
0.25
2.2
Expected Project Duration
...